Houston
Solar panels in Houston: what the city, CenterPoint and your plan decide
By Jake Breaux, registered Texas solar salesperson (TDLR) · Updated · Leer en español
The short version
Solar panels in Houston need a City of Houston solar permit ($91.06 plus a $33.56 admin fee) and CenterPoint's approval to connect. CenterPoint pays participating installers $135 per kW of panels, up to 15 kW. It doesn't buy your extra power. Only your retail electricity company can, and it doesn't have to.
CenterPoint will connect your panels, but it won't buy a single kilowatt-hour they send back. In Houston, buying your extra power is up to your retail electricity company. Pick the wrong plan and the savings a salesperson shows you can shrink in the first mild month.
How much do solar panels cost in Houston?
Solar panel prices in Houston come from each installer's quote, because no public agency publishes a local price per watt. Inside city limits, every job adds a $91.06 City permit and a $33.56 admin fee. A participating installer credits a CenterPoint incentive of $135 per kW of panels, up to 15 kW, on your invoice.
- At the 15 kW cap, CenterPoint's incentive comes to $2,025. Only existing single-family houses qualify. New construction and homes that already have solar don't.
- The federal homeowner tax credit for solar ended for new installs.
- Texas Tax Code § 11.27 exempts from property tax the value that solar adds to your home. The exemption covers a battery that stores the solar energy too.
- A solar loan usually runs 10 to 25 years. A lease or a PPA (power purchase agreement, where you pay per kWh the panels make) usually runs 20 to 25, with a yearly price increase of often 2.9% to 3.9%. All four ways to pay are compared in our guide to whether solar is worth it in Texas.
What the panels save you is the power you stop buying. CenterPoint's delivery charge alone is 6.53 cents per kWh plus $4.90 a month, as printed on plan labels on Power to Choose (read November 7, 2026). At 1,000 kWh that's about $70 a month before any energy. Plan prices are on Houston electricity rates.
Who buys extra solar power in Houston?
Your retail electricity company, if it chooses to. CenterPoint says it doesn't buy power or offer net metering (a credit for exported power at the price you pay). Power to Choose, the state's plan site, says you can sell excess power only to the company you buy electricity from, and that company isn't required to buy it.
- Some retailers buy your extra power only if you're on one of their own plans.
- CenterPoint reprograms your meter to read what you send to the grid. Your retailer turns those readings into credits, or doesn't.
- Watch the bill-credit plans. On November 6, 2026, 8 of the 10 cheapest-looking CenterPoint-area plans at 1,000 kWh had a bill credit or other condition. The cheapest of those plans listed 6.8 cents per kWh at 1,000 kWh and 19.8 cents at 500 kWh.
- Solar cuts how much you buy. A home that drops from 1,000 kWh to 500 in a sunny spring month can lose the credit and pay nearly three times the headline rate.
How buyback plans pay, and what Texas law says about them, is onTexas solar buyback plans.
How do you connect solar panels to CenterPoint?
Your installer applies to CenterPoint online, and nothing gets switched on until CenterPoint issues Permission to Operate. CenterPoint lists five steps: the application, its review of the design, construction, its review of the finished system, and then Permission to Operate.
- CenterPoint signs an Interconnection Agreement with you and reprograms the meter.
- Your installer handles the equipment, the design and every permit.
- You handle the paperwork with the installer, your retail electricity company and, if you have one, your HOA.
- Bought a home that already has panels? CenterPoint says to email Residential.DG@CenterPointEnergy.com and go through its application before you turn them on.
Do you need a permit for solar panels in Houston?
Yes. Inside city limits, the City of Houston requires a Solar Panel Permit (code HPWCODE1119) with plan review and an inspection. It costs $91.06 plus a $33.56 admin fee, and plan review can add a fee based on the project's value. Only a licensed contractor registered with the City can apply.
- The contractor applies through iPermits, the City's online permit system, and uploads plans to ProjectDox, its plan review site.
- Since July 15, 2024, registered contractors can use SolarAPP+, plan review software the City brought in with the National Renewable Energy Laboratory. A project filed that way skips the City's traditional plan review.
- SolarAPP+ can't be used where the building code requires design for winds of 140 mph or more. Those projects get ordinary plan review.
- A home in another city, such as Pasadena or Sugar Land, follows that city's own permit office.
Can a Houston HOA stop you from installing solar panels?
Not in most cases. Texas Property Code § 202.010 voids HOA rules that prohibit or restrict a homeowner from installing solar, with eight exceptions. The HOA can still require its approval before installation, set rules for where on the roof the panels go, and keep panels off common property.
Apply first and wait for the answer. A system installed without prior approval is one of the eight things the law lets an HOA prohibit. The full list, with the roof rules, is on Texas HOA solar rules.
How often does the power go out in Houston?
In an ordinary year, briefly. In 2025 the average CenterPoint customer lost power 1.13 times, for about 101 minutes in all, outside major storms. Storm years are different. With storms counted, the average was about 72 hours in 2024 and about 39 hours in 2021, the Winter Storm Uri year.
- CenterPoint's 2025 figures beat its state standard of 1.24 outages and 126 minutes.
Every utility's year-by-year record is onTexas power outages by utility.
How do you check a Houston solar company?
Look it up with the Texas Department of Licensing and Regulation (TDLR). Since September 1, 2026, solar retailers and solar salespeople who sell to Texas homes must be registered with TDLR, unless they sell for an electrical contractor. Look up both the company and the person at your door. TDLR's license search is linked from its residential solar page.
- The contract has to carry the names and registration numbers of both the company and the salesperson (Occupations Code § 1806.154).
- You can cancel a home solar contract by written notice until the fifth business day after you sign it (§ 1806.156).
- An electrical contractor and its own employees don't register as solar retailers (§ 1806.004). If a company isn't in the solar search, check TDLR's electrician licenses too.
The search steps, and what the contract must say, are onTDLR solar registration.
Our solar subscription in Houston
Our solar subscription is the way to get panels without buying them. The provider owns, insures and maintains the system, so you pay $0 upfront and then pay monthly for the power it makes. The rate rises 1.9% a year, fixed. You can leave after 36 months with no fee.
Every subscription system in Texas comes with a battery, 40 kWh or more. There's no lien on your house. Savings run around 40% of the bill on average, and that figure is an estimate. The home still has to qualify on its roof, its power use and a credit check.See the numbers for your roof.
Sources
Subscription solar is our business, so don't take our word for the contract mechanics. These are the primary sources: check them.
- Solar Panel Permit (HPWCODE1119), City of Houston, Houston Permitting Center
Fee $91.06, admin fee $33.56, plan review fee subject to valuation. Plan review and inspection required. Licensed contractors must register their license with the City and apply through iPermits; plans go through ProjectDox. Statutory authority: Occupations Code chapter 1305 (electricians) and the City electrical code. Read 2026-11-06.
- NEW: SolarAPP+ for Streamlined Solar Panel Permitting, City of Houston, Houston Permitting Center
From July 15, 2024, licensed contractors registered with SolarAPP+ and the City can get rooftop solar permits without traditional plan review. Projects where the basic wind speed design is 140 mph or greater (a windborne debris region) are not eligible. Updated 5/23/2025. Read 2026-11-06.
- Solar Energy: Connecting your System to the Grid, CenterPoint Energy
Five steps: the installer applies online, CenterPoint reviews and accepts the design, the installer builds, CenterPoint reviews the as-built plans, Permission to Operate (PTO) is issued. Who does what: the customer completes paperwork with the installer, the retail electric provider and others such as an HOA; the installer secures permits; the retail provider handles billing and any buy-back; CenterPoint issues the Interconnection Agreement and PTO and reprograms the meter to read exports. A home bought with solar already on it goes through Residential.DG@CenterPointEnergy.com before the system is turned on. Read 2026-11-06.
- Electric technology, CenterPoint Energy
"While we don't buy power or offer net metering, your electric retail provider may offer buy-back programs crediting excess energy sent to the grid." Read 2026-11-06.
- Help save money and energy on installation of residential solar system, CenterPoint Energy
Incentive of $135 per kW of rated DC system size, capped at 15 kW, paid to participating service providers and shown as a credit on the installation invoice. Existing single-family homes in the Houston Electric territory only; new construction and homes with existing solar are not eligible; an interconnection agreement is required. Not a direct-to-customer program. Read 2026-11-06.
- Selling Excess Renewable Power, Power to Choose, Public Utility Commission of Texas
In areas with retail competition you must sell excess power to the company you buy electricity from, and that company is not required to buy it. Some buyers require you to take a specific retail plan. You must sign an interconnection agreement with your delivery utility. Read 2026-11-06.
- Power to Choose plan export and Electricity Facts Labels, Public Utility Commission of Texas
CenterPoint area, 12-month fixed plans, one listing each, read 2026-11-06: 42 plans; 8 of the 10 cheapest at 1,000 kWh carry a bill credit or other condition; the lowest lists 6.8 cents/kWh at 1,000 kWh and 19.8 cents at 500 kWh. Delivery charges as printed on plan labels, read 2026-09-28: 6.413 cents/kWh plus $4.90 a month. Same data as our Houston electricity rates page.
- Property Code Section 202.010, Regulation of Solar Energy Devices, Texas Legislature
(b) an association may not include or enforce a provision that prohibits or restricts a property owner from installing a solar energy device; (c) such a provision is void; (d)(8) it may prohibit a device installed without prior approval. Read 2026-11-06 from tcss.legis.texas.gov.
- Tax Code Section 11.27, Solar and Wind-Powered Energy Devices, Texas Legislature
(a) exempts from property tax the amount of appraised value that arises from installing a solar device primarily for on-site use; (c)(1) the definition includes storing the converted energy. Read 2026-11-06 from tcss.legis.texas.gov.
- Residential Solar Retailers: laws and effective dates, Texas Department of Licensing and Regulation
Beginning September 1, 2026, residential solar retailers and solar salespersons must be registered with TDLR. Cancellation notice may be given on or before the fifth business day after the agreement is signed. The license search is linked from TDLR's residential solar page. Read 2026-11-06.
- Occupations Code Chapter 1806, Residential Solar Retailers, Texas Legislature
§ 1806.004: an electrical contractor that employs people to sell residential solar, and those employees, are exempt from registration. § 1806.154(b): each sale or lease agreement must include the name and registration number of the retailer and the salesperson. § 1806.156(b): the buyer or lessee may cancel by written notice on or before the fifth business day after signing. Read 2026-11-06 from tcss.legis.texas.gov.
- CenterPoint Energy Houston Electric, 2025 Service Quality Report, Public Utility Commission of Texas, Project 59163
CenterPoint's 2025 forced interruptions: 1.13 per customer, about 101 minutes; standard 1.24 and 126 minutes. Same source and figures as our Texas power outages page (read 2026-09-28).
- Annual Electric Power Industry Report (Form EIA-861), U.S. Energy Information Administration
Outage minutes per CenterPoint customer with major events counted: about 72 hours in 2024 and about 39 in 2021. Same source and figures as our Texas power outages page (read 2026-09-28).
Want the numbers for your actual roof?